Outcomes
π WP1: Initial Research & Analysis
π― Objective: Conduct fact-finding and prepare baseline reports.
ποΈ Duration: M1 β M4
π₯ Lead Beneficiary: UTM
π Additional Activities:
- Organise the kick-off meeting
- Conduct surveys on companiesβ and trainersβ needs
- Organise study visits
- Elaborate reports on need findings
π·οΈ Deliverable No. | π Title |
D1 | π Report on needs assessment and surveys of stakeholders |
D2 | π Project management handbook |
π WP2: Development of the NIMP & Equipping the Training Labs
π― Objective: Satisfy urgent needs for graduate employability and prevent long-term skill shortages.
ποΈ Duration: M4 β M20
π₯ Lead Beneficiary: RWTH
π Additional Activities:
- Design/develop NIMP program and curricula
- Develop handbook and teaching materials
- Organise Teach-the-Teacher program
- Equip the NIMP virtual labs
π·οΈ Deliverable No. | π Title |
D3 | |
D4 | π Curricula for NIMP developed |
D5 | π Teaching materials elaborated |
D6 | π§ͺ Equipped educational labs |
D7 |
π WP3: Implementation of NIMP
π― Objective: Deliver and implement the NIMP program at Moldovan partner universities.
ποΈ Duration: M17 β M36
π₯ Lead Beneficiaries: TUM + USARB + USC
π Additional Activities:
- Organise admissions to NIMP
- Deliver scheduled teaching across the three universities
- Co-teaching courses with lecturers from Aachen and BraΘov
- Refine teaching materials for NIMP
π·οΈ Deliverable No. | π Title |
D8 | πΎ Learning materials uploaded on joint Moodle platform |
D9 | π NIMP implemented |
π WP4: Quality Assurance, Evaluation and Sustainability
π― Objective: Ensure project quality and long-term impact.
ποΈ Duration: M2 β M36
π₯ Lead Beneficiary: UTBV
π Additional Activities:
- Establish QA Body, Advisory Group, and External Evaluator
- Organise QA workshop
- Hold 6 Advisory Group virtual meetings with reports
- Collaborate with External Evaluator on evaluation reports
π·οΈ Deliverable No. | π Title |
D10 | |
D11 | π§Ύ QA external evaluation reports |
π WP5: Dissemination and Exploitation
π― Objective: Raise visibility, share results, and engage target audiences.
ποΈ Duration: M1 β M36
π₯ Lead Beneficiaries: TUM + USARB + USC
π Additional Activities:
- Develop project identity and website
- Implement online/offline dissemination tools
- Organise dissemination seminar for NIMP candidates
- Publish project result articles
π·οΈ Deliverable No. | π Title |
D12 | π’ Dissemination and exploitation plan |
D13 | π° Articles on project results |
π WP6: Project Management
π― Objective: Coordinate activities, monitor progress and ensure smooth implementation.
ποΈ Duration: M1 β M36
π₯ Lead Beneficiary: Technical University of Moldova (TUM)
π Additional Activities:
- Facilitate communication and collaboration
- Monitor progress, budgets, and risks
- Coordinate across work packages
- Ensure quality of outputs and deliverables
π·οΈ Deliverable No. | π Title |
D14 | π 6 Steering Committee Meetings & 12 Management Meetings performed |
D15 | π Mid-term Progress Report |
D16 | π Report on measurement of KPIs in LFM |